Impact of Non-Completion pre rollout activities in APT 2.0

 

Impact of Non-Completion pre rollout activities in APT 2.0


SL No

Activity

Impact

1

Device Registration

Not able to work in 2.0 if device not registered

2

TOTP App Installation

Not able to login to application if not done

3

Office Master Updations

Proper workflow will not happen in APT 2.0 Solution

4

Establishment Data (Post and Cadre)/Validation

Not able to map staffs to the roles if not done properly

5

Employee Data Validation

Not able to map staffs to the roles if not done properly

6

Authority Mapping for all the Posts

Prerequisite for Role Assignment

7

Role Assignment

Counter operations cannot be possible if not assigned

8

Budget Updation

This is required to validate the consumption and pending balance of the Budget allocation

9

Schedule Creation/Modification

Cannot dispatch bags if not created properly

10

DML Maintenance

Cannot close bags if not created

11

Treasury data validation (Authorised balances and cash office/bank mapping)

Post Office cash transactions will not happen if not mapped properly

Bill payment services

12

Create Sets for all Mail offices

Mail transmission will not happen if not created

13

On-board Outsource Resource/ Substitute (If required)

Outsource Staff and Substitutes will not be able to work

14

Create Temporary Arrangement (If required)

Create problem if the assigned staff is on leave on Roll Out day

15

Customer data validation- Franking

If not done properly customer data will not flow in to 2.0

16

Customer data validation - PDA

If not done properly, customer data will not flow into APT 2.0

17

Customer data validation - BNPL Customer: Customer data to be verified and Notional Balance to be updated Advance Customer : Customer Data to be verified

If not done properly customer data will not flow into APT 2.0

18

Bank Details Configuration by PAO (Remittance & Drawing Accounts)

If not done, remittance and drawal from bank will not happen

19

Mail office Mapping

Duty allocation will not be possible which will lead to non working of the Offices

20

Work Assignment

Without work assignment, officials will not be able to work in Mail Offices

21

Update GPF Balance

Will impact the GPF Account operations

22

Role Assignment

Modules cannot be open if required role not assigned

23

Batch – Beat Management

If not done Postman duties will be disrupted

24

Bulk Addressee and Bulk Payee Mapping

If not while booking bulk customers it will take more time

25

Counter Configuration

If not done not able to do Counter work

26

Cheque Validation

If not done cheque issuance will be a problem

27

Pensioners Data Validation

Pension disbursement will be an issue if not validated

28

Leave Balance Update

Impact the Leave Balance of the official

29

Customer data validation (PDA)

If not done PDA balance mismatch issue will occur

30

Pay- Roll

Will impact the pay, pension, recover, advance, recovery etc.. of the officials